CompTIA Project+ (PK0-004) — Question 179

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Answer options

Correct answer: B

Explanation

Option B is correct because it specifies that the scheduler will directly apply the current status to the baseline of the schedule, providing an accurate and structured report. The other options involve unnecessary steps or reporting to individuals who are not best positioned to assess project progress, such as the project manager or project champion.