CompTIA Project+ (PK0-004) — Question 155

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

Answer options

Correct answer: D

Explanation

The correct action is to revisit the contingency plan and provide corrective actions, as it specifically addresses unexpected issues that could jeopardize the project. The other options do not directly resolve the problem at hand or could lead to further complications in the testing process.