CompTIA Project+ (PK0-004) — Question 151
Which of the following shows projected project expenditures?
Answer options
- A. Work breakdown structure
- B. Cash flow schedule
- C. Cash burn rate
- D. Budget milestone
Correct answer: A
Explanation
The Work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to accomplish the project objectives, which includes projected expenditures. The other options, while related to project finance, do not specifically outline projected expenditures in the same structured manner as WBS.