CompTIA Project+ (PK0-004) — Question 149
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.
Which of the following best describes what the PM should work on FIRST?
Answer options
- A. Project charter
- B. Project schedule
- C. Meeting agenda
- D. Responsibility assignment matrix
- E. Risk register
Correct answer: B
Explanation
The correct answer is B, as the project schedule outlines the timeline and milestones necessary to achieve the expected outcomes. Without a clear schedule, the team may struggle to focus effectively on their goals. While the project charter, meeting agenda, responsibility assignment matrix, and risk register are all important documents, they are secondary to establishing a comprehensive project schedule.