CompTIA Project+ (PK0-004) — Question 146

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

Answer options

Correct answer: B

Explanation

The correct answer is B, MOA, which outlines the terms of the agreement including provisions like overtime. The other documents, while important, do not specifically cover the contractual obligations regarding overtime hours.