CompTIA Project+ (PK0-004) — Question 122

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?

Answer options

Correct answer: B

Explanation

The correct answer is B because resource analysis and a Gantt chart are essential for understanding the allocation of personnel and tracking project timelines. If these were neglected, it could lead to a lack of clarity regarding resource availability and project scheduling, resulting in the department manager's uncertainty. The other options, while important, do not directly address the resource and timeline issues that would explain the status inquiry.