CompTIA Project+ (PK0-004) — Question 113

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?

Answer options

Correct answer: B

Explanation

The correct answer is B because crashing the schedule for the vendor would have ensured that their tasks aligned with the project team's progress, allowing for timely testing. Option A suggests delaying the project team, which would not resolve the dependency issue. Option C relies on the project team to push the vendor, which may not be effective, and Option D is incorrect as it implies the vendor should slow down, further complicating the timeline.