CompTIA Project+ (PK0-004) — Question 111

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Answer options

Correct answer: A

Explanation

The correct action is to revise the project plan (A) because it is necessary to adjust the plan to address the delays while keeping the completion date and quality intact. Updating the issue log (B) may help track issues but does not directly address the delays. Requesting additional funding (C) may not be relevant if the project scope and quality cannot change. Issuing a change request (D) is unnecessary since the completion date is fixed.