CompTIA Project+ (PK0-004) — Question 109
In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
Answer options
- A. a dedicated resource pool
- B. an allocated resource pool
- C. a shared resource pool
- D. a benched resource pool
Correct answer: B
Explanation
The correct answer is B, as an allocated resource pool consists of resources specifically assigned to projects, making them the first point of contact for project needs. The other options, like the dedicated resource pool (A) and shared resource pool (C), may not have resources readily available, while a benched resource pool (D) indicates resources that are not currently assigned but may not be immediately accessible.