CompTIA Project+ (PK0-004) — Question 1
A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?
Answer options
- A. Network diagram
- B. Ishikawa diagram
- C. WBS
- D. Gantt chart
Correct answer: A
Explanation
The Network diagram is the most beneficial tool for establishing the sequencing and duration of project activities, as it visually represents the relationships and dependencies between tasks. The Ishikawa diagram is used for root cause analysis, the WBS helps in breaking down tasks but does not show sequencing, and the Gantt chart is useful for scheduling but does not provide the detailed dependencies that a Network diagram does.