CompTIA Network+ (N10-009) — Question 189

A network architect is implementing an off-premises computing facility and needs to ensure that operation will not be impacted by major outages. Which of the following should the architect consider?

Answer options

Correct answer: A

Explanation

A hot site is a backup facility that is fully operational and ready to take over immediately in case of a major outage, making it the best option for ensuring continuous operations. The other options, such as DCI and Direct Connect, do not specifically address the need for immediate operational capability during outages, and the active-passive approach may not provide the same level of immediacy and availability as a hot site.