CompTIA Network+ (N10-009) — Question 180

A network administrator needs to fail over services to an off-site environment. This process will take four weeks to become fully operational. Which of the following DR concepts does this describe?

Answer options

Correct answer: C

Explanation

The correct answer is C, Cold site, which refers to an off-site backup facility that requires significant time to become operational. A Hot site (A) is fully operational immediately, a Warm site (B) is partially equipped and takes less time than a Cold site, and the Active-active approach (D) involves multiple live sites working simultaneously, which does not apply here.