CompTIA Network+ (N10-008) — Question 780

A network engineer performed a detailed network analysis. The engineer has decided to update the STP port cost in order to optimize the network. Which of the following processes should the engineer use to gain approval for the network optimization?

Answer options

Correct answer: D

Explanation

The correct process for obtaining approval for network changes is Change management (D), as it is specifically designed to handle modifications in the network infrastructure. Business continuity (A), disaster recovery (B), and incident response (C) focus on different aspects of network operations and recovery, rather than on the approval process for changes.