CompTIA Network+ (N10-007) — Question 93
A network technician is installing and configuring a new router for the sales department. Once the task is complete, which of the following needs to be done to record the change the technician is making to the company network?
Answer options
- A. Change management
- B. Network diagrams
- C. Inventory report
- D. Labeling report
Correct answer: A
Explanation
The correct answer is A, as change management specifically involves documenting alterations to the network infrastructure. Options B, C, and D, while important for network maintenance, do not primarily focus on the documentation of changes made during installation and configuration.