CompTIA Network+ (N10-007) — Question 586

The management team has instituted a 48-hour RTO as part of the disaster recovery plan. Which of the following procedures would meet the policy's requirements?

Answer options

Correct answer: C

Explanation

Option C is correct because it directly aligns with the 48-hour RTO by ensuring that all systems are operational within that time frame. Option A is incorrect as recovering data loss does not guarantee system recovery within the specified RTO. Option B addresses network downtime rather than overall system recovery, making it irrelevant. Option D pertains to backup maintenance, which does not ensure the recovery of systems within the required timeframe.