CompTIA Network+ (N10-007) — Question 107
A network engineer is designing a new IDF in an old building. The engineer determines the equipment will fit in a two-post rack, and there is power available for this equipment. Which of the following would be the FIRST issue to remediate?
Answer options
- A. Air flow and cooling
- B. UPS capability
- C. Circuit labeling
- D. Power redundancy
Correct answer: A
Explanation
The primary concern in setting up network equipment is ensuring proper air flow and cooling to prevent overheating, which can damage the hardware. While UPS capability, circuit labeling, and power redundancy are important, they become secondary issues once the equipment's environmental conditions are addressed.