CompTIA Network+ (N10-006) — Question 39

A company suffers an outage due to a bad module in a core switch.
Which of the following is the proper order of troubleshooting?

Answer options

Correct answer: B

Explanation

The correct answer is B, as establishing a plan of action is crucial before attempting to troubleshoot effectively. Options A and D suggest starting at different layers of the OSI model without a strategic plan, which may lead to inefficient troubleshooting. Option C outlines a theory-based troubleshooting approach, but without a clear plan, it may lack direction.