CompTIA ITF+ (FC0-U61) — Question 165

Which of the following would be the most cost-effective method to increase availability?

Answer options

Correct answer: C

Explanation

A continuity plan is designed to ensure that essential functions can continue during and after a disaster, making it a cost-effective way to maintain availability. In contrast, redundant equipment and disaster recovery sites involve higher capital expenditures, and while scheduled maintenance is important, it does not directly increase availability in the same way a continuity plan does.