CompTIA Cloud+ (CV0-003) — Question 349

A systems administrator is helping to develop a disaster recovery solution. The solution must ensure all production capabilities are available within two hours. Which of the following will BEST meet this requirement?

Answer options

Correct answer: A

Explanation

A hot site is the most effective option because it is fully equipped and operational, allowing for immediate recovery and minimal downtime. A warm site, while partially equipped, would not guarantee the two-hour requirement due to the need for additional setup. A backup site and a cold site would involve longer recovery times, making them unsuitable for this urgent requirement.