A clinic is planning to move its business management software from a local server to a privately hosted service. The clinic operates only on weekdays, and the data growth rate is slow. The software application requires other third-party tools to be present for efficient operations. Given the following objectives:
• Minimal downtime
• Cost savings
• High availability
Which of the following is the best migration strategy to achieve these objectives?
Answer options
- A. Performing a P2V and implementing fault tolerance
- B. Implementing V2V and setting up cross-services migration
- C. Performing a V2P and implementing autoscaling
- D. Setting up a new infrastructure, installing management software, and implementing fault tolerance
Correct answer: A
Explanation
The correct answer is A because performing a P2V (Physical to Virtual) migration allows for a seamless transition with minimal downtime, while implementing fault tolerance ensures high availability. The other options either do not align with the requirement for minimal downtime or introduce unnecessary complexity and costs.