CompTIA Cloud+ (CV0-002) — Question 151

A manufacturing company has the following DR requirements for its IaaS environment:
✑ RPO of 24 hours
✑ RTO of 8 hours
The company experiences a disaster and has a two-site hot/cold configuration. Which of the following is the BEST way for the company to recover?

Answer options

Correct answer: C

Explanation

The correct choice is C because it involves rebuilding the site from the cold site, which meets the RTO of 8 hours. Options A and B do not ensure compliance with the company's RPO and RTO requirements, and option D involves unnecessary complexity and potential delays in recovery.