CompTIA Cloud Essentials+ (CLO-002) — Question 11

After performing an initial assessment of a cloud-hosted architecture, a department wants to gain the support of upper management.
Which of the following should be presented to management?

Answer options

Correct answer: A

Explanation

The project charter is essential as it outlines the project's objectives, scope, and stakeholders, making it crucial for gaining executive support. The feasibility study, while important, is typically for assessing viability rather than securing approval. Managed services and a pilot may support the project later but do not directly communicate the project's purpose and alignment with management needs.