CompTIA Cloud Essentials+ (CLO-001) — Question 23
Which of the following is the MOST important service management consequence of elastic capacity?
Answer options
- A. The need for better application development
- B. The need for better security management
- C. The need for good performance monitoring and management
- D. The need to improve the fulfillment and provisioning process
Correct answer: C
Explanation
The correct answer, C, highlights that with elastic capacity, monitoring and managing performance becomes crucial to ensure resources are utilized efficiently. Options A, B, and D, while important, do not directly address the immediate need for performance oversight that arises from the variability in resource allocation associated with elastic capacity.