An organization plans to deploy new software. The project manager compiles a list of roles that will be involved in different phases of the deployment life cycle. Which of the following should the project manager use to track these roles?
Answer options
- A. CMDB
- B. Recall tree
- C. ITIL
- D. RACI matrix
Correct answer: D
Explanation
The RACI matrix is specifically designed to clarify roles and responsibilities in a project, making it the most suitable choice for tracking involvement during the deployment life cycle. The CMDB is used for managing configuration items, the Recall tree is not a standard project management tool, and ITIL provides a framework for IT service management but does not track roles directly.