CompTIA CASP+ (CAS-004) — Question 536

A client is adding scope to a project. Which of the following processes should be used when requesting updates or corrections to the client's systems?

Answer options

Correct answer: B

Explanation

The correct answer is B because the change control board is responsible for assessing and approving changes to project scope, ensuring that all modifications are properly evaluated. The other options involve individuals or roles that do not have the authority or process in place to approve changes, making them incorrect in this context.