CompTIA CASP+ (CAS-003) — Question 218
A project manager is working with a software development group to collect and evaluate user scenarios related to the organization's internally designed data analytics tool. While reviewing stakeholder input, the project manager would like to formally document the needs of the various stakeholders and the associated organizational compliance objectives supported by the project.
Which of the following would be MOST appropriate to use?
Answer options
- A. Roles matrix
- B. Peer review
- C. BIA
- D. SRTM
Correct answer: D
Explanation
The SRTM (Stakeholder Requirements Traceability Matrix) is specifically designed to document and track stakeholder needs and compliance objectives, making it the most suitable choice. While a Roles matrix outlines responsibilities, Peer review assesses quality, and BIA (Business Impact Analysis) focuses on risk, none of these options effectively capture stakeholder requirements in the same comprehensive manner as the SRTM.