CompTIA A+ Core 2 (220-1202) — Question 15

A network technician notices that most of the company's network switches are now end-of-life and need to be upgraded. Which of the following should the technician do first?

Answer options

Correct answer: C

Explanation

The first step in the change management process is to propose the change, which allows for the necessary discussions and evaluations to take place. Implementing, approving, or scheduling the change cannot occur without a formal proposal outlining the need for the upgrades and the plan to address them.