CompTIA A+ Core 2 (220-1102) — Question 652

A change advisory board just approved a change request. Which of the following is the MOST likely next step in the change process?

Answer options

Correct answer: A

Explanation

The most likely next step after a change request is approved by a change advisory board is to proceed with end user acceptance, as it ensures that the users agree with and are ready for the change. Performing risk analysis, communicating to stakeholders, and sandbox testing are important but typically occur earlier in the change process or concurrently with user acceptance.