CompTIA A+ Core 2 (220-1102) — Question 437

Which of the following should be documented to ensure that the change management plan is followed?

Answer options

Correct answer: A

Explanation

Documenting the scope of the change is essential as it defines the boundaries and impact of the change, ensuring the change management plan is effectively executed. While the purpose, rollback plan, and risk analysis are important, they do not specifically delineate what is included in the change, which is critical for adherence to the plan.