A technician is working on a virtual server migration project. The technician has already completed the SOW; however, the servers will not work without a critical network configuration that was missed in the original SOW. The technician needs to make the adjustments quickly.
Which of the following best practice processes should the technician perform NEXT?

Answer options

Correct answer: E

Explanation

The correct answer is E because documenting changes and executing the work is essential in ensuring that all alterations are tracked and implemented correctly. Options A, B, C, and D all involve additional steps for approvals or notifications that may delay the process, which is not ideal when urgent changes are needed.