CompTIA A+ Core 2 (220-1002) — Question 186
A business unit wants to upgrade the current version of its loan processing software. A manager is putting together a change management request and gathering information on the software.
Which of the following would be MOST important during this phase of the request process?
Answer options
- A. Back-out plan
- B. End-user acceptance
- C. Risk analysis
- D. Test plan
Correct answer: C
Explanation
The most critical component during this phase is the Risk analysis, as it helps identify potential issues and impacts of the software upgrade. While a Back-out plan, End-user acceptance, and Test plan are also important, they are secondary to understanding the risks involved to ensure a smooth transition.