Citrix Virtual Apps and Desktops 7 Advanced Configure and Manage — Question 70

Scenario: A Citrix Engineer is working on an existing Citrix Virtual Apps and Desktops environment with two Delivery Controllers each in Primary zone and
Secondary zone located in two different datacenters respectively. Due to an outage in the Primary zone datacenter, both Delivery Controllers in the Primary zone failed to start.
Which three statements will be true in this scenario? (Choose three.)

Answer options

Correct answer: A, C, D

Explanation

The correct answers are A, C, and D because when the Primary zone's Delivery Controllers fail, site performance will decline (A), Studio will lose connection to the site (C), and no connections can be established to VDA machines in the Primary zone (D). However, connections to VDA machines in the Secondary zone may still be possible, making option B incorrect, and existing sessions in the Primary zone would not be disconnected immediately, so option E is also incorrect.