CCDE: Cisco Certified Design Expert (Practical) — Question 4

A small organization of 20 employees is looking to deliver a network design service for modernizing customer networks to support advanced solutions.
* Project scope and weekly progress should be visualized by the management.
* Always consider feedback and make changes accordingly during the project.
* Should consider flexibility to change scope at the point of time.
Which project methodology meets the requirements and have the least impact on the outcome?

Answer options

Correct answer: D

Explanation

Kanban is ideal for this scenario as it allows for continuous delivery and flexibility in managing changes to the project scope while visualizing progress effectively. Scrum, while agile, is more structured and may not adapt as fluidly to frequent changes in scope compared to Kanban. LEAN and Six-Sigma focus on waste reduction and process improvement, which are less aligned with the dynamic requirements outlined.