CCDE: Cisco Certified Design Expert (Practical) — Question 104
Various teams in different organizations within an enterprise are preparing low-level design documents to capture network parameters using a Waterfall project model:
• hardware sizing and power consumption
• Layer 2 and layer 3 services parameters
• configuration of all control plane protocols
Input from relevant stakeholders was captured at the start of the project, and the project scope has been defined based on the parameters above. What impact will it have on documentation and project deliverables if the stakeholders ask to have changes earned out in the network before the information has been captured?
Answer options
- A. Significant effort and time are required
- B. Rework is expected before the delivery
- C. This provides more opportunity to think outside the box
- D. This provides a flexible approach to incorporate changes
Correct answer: B
Explanation
The correct answer is B because requesting changes before documentation is complete will inherently lead to rework. Options A and D suggest significant effort or flexibility, but they do not address the specific expectation of redoing work. Option C implies a positive aspect that doesn't align with the context of needing to rework existing plans.