Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 405
An engineer must start a software upgrade on a Cisco Nexus 5000 Series Switch during a zone merge. What is the result of this action?
Answer options
- A. The upgrade stops
- B. The zone merge pauses until the upgrade completes
- C. The zone merge stops
- D. The zone merge executes and then the upgrade completes
Correct answer: A
Explanation
The correct answer is A because when a software upgrade is initiated during a zone merge on a Cisco Nexus 5000 Series Switch, the upgrade process halts. Options B, C, and D are incorrect as they imply that the zone merge can continue or pause, which is not the case; the ongoing upgrade takes priority, stopping the process.