Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 364

An engineer is implementing VSANs on a Cisco MDS 9000 Series Switch with a native Fibre Channel. The deployment must meet these requirements:
• The host on port fc1/1 must be assigned to VSAN 10.
• The port channel 10 ISL must pass multiple VSANs, including VSAN 10.

Which configuration set meets these requirements?

Answer options

Correct answer: B

Explanation

Option B is correct because it involves creating VSAN 10 in the VSAN database, binding it to port fc1/1, enabling trunking on the ISL, and allowing VSAN 10, which meets all requirements. The other options either do not correctly configure the ISL for multiple VSANs or misconfigure the necessary bindings and settings.