Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 307
An engineer must deploy a Cisco UCS C-Series Server with a single VIC 1455 integrated into a Cisco UCS Manager cluster. Two fiber connections are available, and the deployment has no fabric extenders. Which set of actions accomplishes this goal?
Answer options
- A. Reset the system using Cisco IMC to its factory default settings. Attach VIC port 1 and 3 to Fabric Interconnects.
- B. Configure VIC attached ports as Uplink ports on fabric interconnects. Insert 1000Base-T RJ45 SFP in VIC port 1 and 3.
- C. Reset the system using Cisco IMC to its factory default settings. Insert 1000Base-T RJ45 SFP in VIC port 1 and 3.
- D. Configure VIC attached ports as Uplink ports on fabric interconnects. Attach VIC port 1 and 3 to Fabric Interconnects.
Correct answer: A
Explanation
The correct answer is A because resetting the system to factory defaults ensures a clean configuration, followed by connecting the VIC ports to the Fabric Interconnects, which is necessary for communication. Options B and D involve configuring ports as Uplink ports, which is not needed for this setup with no fabric extenders, while option C lacks the necessary connection to the Fabric Interconnects.