Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 17
Which two components should be checked when a Cisco Nexus 9000 Series Switch fails to boot using POAP? (Choose two.)
Answer options
- A. POAP feature license
- B. DHCP server to bootstrap IP information
- C. image noted in the script file against switch bootflash
- D. script signed with security key
- E. TFTP server that contains the configuration script
Correct answer: B, E
Explanation
The correct answers are B and E because the DHCP server is essential for providing the switch with the necessary IP information to bootstrap, and the TFTP server is required to host the configuration script needed for the boot process. Options A, C, and D, while potentially relevant in other contexts, are not directly required for the boot process to succeed via POAP.