Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 167

An engineer is performing an ISSU upgrade on the Cisco MDS 9000 Series Switch. What is the impact on the control plane of the switch?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the control plane experiences downtime of less than 80 seconds during the ISSU upgrade, ensuring minimal disruption. Options B and C indicate longer downtime periods, which are not accurate for this upgrade process, while option D incorrectly states that the control plane remains fully operational throughout the update.