Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 135
What are two requirements when planning a Cisco HyperFlex All Flash standard cluster installation using three Cisco HX240c M5 Series servers? (Choose two.)
Answer options
- A. If the Jumbo MTU option in the HyperFlex installer is enabled, then jumbo frames do not have to be enabled on the upstream switches.
- B. This cluster deployment type must support a mix of HDD and SSD.
- C. The servers must be discovered, unassociated, and connected to each fabric interconnect.
- D. If the Jumbo MTU option in the HyperFlex installer is enabled, then jumbo frames must also be enabled on the upstream switches.
- E. The hypervisors must be installed to Cisco FlexFlash SD cards.
Correct answer: C, D
Explanation
The correct answer is C and D because for a successful installation, the servers must be properly discovered and connected to the fabric interconnects, and enabling Jumbo MTU in the installer necessitates that jumbo frames are also configured on the upstream switches. Options A and B are incorrect as they misinterpret the requirements for jumbo frames and the types of storage required for this cluster deployment.