Implementing Cisco Application Centric Infrastructure (DCACI) — Question 55

New ESXi hosts are procured in a data center compute expansion project. An engineer must update the configuration on the Cisco APIC controllers to support the addition of the new servers to the existing VMM domain. Which action should be taken to support this change?

Answer options

Correct answer: D

Explanation

The correct action is D because mapping the leaf interface selector to the appropriate AEP enables the new ESXi hosts to connect to the VMM domain correctly. Options A and B do not directly relate to supporting the integration of new servers, while option C, although relevant to VLANs, does not address the specific requirement of linking the leaf interface with the VMM domain.