Implementing Cisco Application Centric Infrastructure (DCACI) — Question 311
Which requirement must be met for the inter-pod network when connecting a remote leaf to a Cisco Application Centric Infrastructure fabric?
Answer options
- A. less than 150ms end-to-end latency
- B. dynamic host configuration protocol relay configuration on the upstream router
- C. multicast bidirectional PIM support
- D. border gateway protocol underlay for VTEP reachability
Correct answer: B
Explanation
The correct answer is B because a dynamic host configuration protocol relay on the upstream router is essential for the inter-pod connectivity, ensuring IP address assignment and communication. Options A, C, and D do not directly pertain to the necessary configurations for connecting a remote leaf in this context.