Implementing Cisco Application Centric Infrastructure (DCACI) — Question 144

A Cisco ACI fabric is connected to an external Cisco Catalyst switch. Which set of actions must be taken for Cisco ACI leaf and spine switches to be managed from the management port?

Answer options

Correct answer: D

Explanation

The correct answer is D because it outlines the need to provide a default/common contract through the out-of-band EPG, which allows for proper management access. Options A, B, and C do not correctly specify the necessary management contracts or mix up the roles of the networks and EPGs involved.