Implementing Cisco Application Centric Infrastructure (DCACI) — Question 125

An engineer wants to monitor all configuration changes, threshold crossing, and link-state transitions in a Cisco ACI fabric. Which action must be taken to receive the required messages?

Answer options

Correct answer: C

Explanation

The correct answer is C because including Audit Logs and Events in the Syslog source policy ensures that all relevant messages regarding configuration changes and events are captured. The other options do not provide the necessary configurations to capture these specific types of messages effectively.