Implementing Cisco Application Centric Infrastructure (DCACI) — Question 110

What two actions should be taken to deploy a new Cisco ACI Multi-Pod setup? (Choose two.)

Answer options

Correct answer: D, E

Explanation

The correct actions involve ensuring that the TEP pool of the new pod is routable across the IPN and increasing the interface MTU for all IPN routers to support VXLAN traffic. Configuring MP-BGP is important but not required specifically for a new Multi-Pod setup, while connecting all spines to the IPN is a standard action but not a prerequisite for deployment. Establishing anycast RP is also not necessary in this context.