Troubleshooting Cisco Data Center Infrastructure (DCIT) — Question 49
A Cisco UCS C-Series Server powers off due to a power outage. The server should turn on when the power is restored with a fixed delay of 3 minutes. However, it remained powered off for more than 3 minutes after the engineer powered it back online. Which two actions resolve the issue? (Choose two.)
Answer options
- A. Configure the power-restore-policy.
- B. Configure the power restore last-state policy.
- C. Configure power sync policy.
- D. Set the delay fixed value to 3.
- E. Set the delay value to 180.
Correct answer: B, E
Explanation
The correct answer includes B, which sets the server to return to its last state after power is restored, ensuring it turns on automatically. E is also correct as it specifies the delay in seconds, ensuring the server waits the correct amount of time before powering on. The other options do not address the specific delay or last-state configuration needed for this scenario.