Implementing Cisco Catalyst Center and SD-WAN Essentials (ENTNSS) — Question 24

An engineer must implement a Cisco Secure Internet Gateway by using Cisco Umbrella over a gateway site that has the NBAR protocol enabled. Which action is required after the tunnel interface is configured on a Cisco vManage device?

Answer options

Correct answer: C

Explanation

The correct answer is C, as setting the probe path is essential for directing traffic through the tunnel interface. Options A and B are related to different configurations that do not directly pertain to the tunnel setup, while option D, while relevant to NBAR, does not follow the tunnel interface configuration step.