Designing Cisco Enterprise Wireless Networks (ENWLSD) — Question 181
An engineer must design AP placements for a new branch office that contains two floors. The engineer uses Ekahau to complete the predictive survey. To calculate the signal bleed through between floors, the engineer creates a building, adds the floors, and attenuations areas. After the scale is set, what else must be added on the floors to accurately measure the signal bleed at a specific location?
Answer options
- A. Choose the access point models.
- B. Start the auto planner.
- C. Add alignment points.
- D. Draw in coverage areas.
Correct answer: C
Explanation
The correct answer is C, as adding alignment points is essential for determining the exact locations where signal bleed can occur between floors. The other options, while relevant to the design process, do not specifically address the need to measure signal bleed at a defined position.