Designing Cisco Wireless Enterprise Networks (WIDESIGN, legacy) — Question 23
Which three components and tasks should be considered while planning the site survey? (Choose three.)
Answer options
- A. Determine the project scope, type of deployment, timeline, scale, budget, and users
- B. Determine project stakeholders
- C. Determine customer training requirements
- D. Determine AP and controller placement
- E. Determine the customer applications that the network will support
- F. Determine radio spectrum and channel allocation
- G. Schedule customer end user interviews
Correct answer: A, B, E
Explanation
The correct answers A, B, and E address essential considerations for a site survey. A outlines the foundational elements, B focuses on key individuals involved in the project, and E ensures understanding of the applications to support. Options C, D, F, and G, while important, are not primary components for initial planning of the site survey.