Check Point Certified Security Administrator (CCSA) R80 — Question 334

Which message indicates IKE Phase 2 has completed successfully?

Answer options

Correct answer: A

Explanation

The correct answer is A, 'Quick Mode Complete', which confirms that IKE Phase 2 has successfully finished establishing the Security Associations. The other options refer to different modes that do not indicate the completion of Phase 2.